Rinconada WTP Update

Below are two progress pictures showing the work inside the existing substation, as well as new ductbank and foundation work for the new standby generator that will be installed shortly. This work is in preparation for a 96-hour plant-wide shutdown in December, the first of 3 plant-wide shutdowns required to perform the upgrades under this contract.