Below are two progress pictures showing the work inside the existing substation, as well as new ductbank and foundation work for the new standby generator that will be installed shortly. This work is in preparation for a 96-hour plant-wide shutdown in December, the first of 3 plant-wide shutdowns required to perform the upgrades under this contract.
BCI Main Office
445 Boulder Ct.
Pleasanton, CA. 94566
Phone: (510) 657-3686
Fax: (510) 657-3688License and DIR
CSLB: 679326
DIR: 1000000447Certifications
Alameda County Transportation Commission LBE: BLO20170707-01
Categories
- Electrical (38)
- General Contracting (22)
- Mechanical (14)
-
Recent Posts
- New Main Office
- SFPUC Southeast WPCP Disinfection Upgrades
- BART Substation RRY Project
- EBMUD Rate Control Station Rehab
- Gilroy WWTP Preanoxic Basin Project
- SFPUC Groundwater Supply Well Stations
- SJWPCP Digester Gas Compressor Project
- BART Transformer Replacement Projects
- Folsom Dam Project Update
- San Jose Water Company – Vickery Tank Project
- BCI Featured in SMW Local 104 Fall Newsletter
- Emergency Ventilation Fans
- Rinconada WTP Residuals Management Project
- SFPUC San Antonio Pipeline (Sunol)
- Warm Springs tunnel ventilation
- VSFCD Influent Pump Station
- VTA Milpitas / Barryessa Extension Update
- VTA BRT Improvements nearing completion
- BART 19th Street Station Entrance Enclosure Pilot
- SSF WPCP Demolition Activities