- New Main Office
- SFPUC Southeast WPCP Disinfection Upgrades
- BART Substation RRY Project
- EBMUD Rate Control Station Rehab
- Gilroy WWTP Preanoxic Basin Project
- SFPUC Groundwater Supply Well Stations
- SJWPCP Digester Gas Compressor Project
- BART Transformer Replacement Projects
- Folsom Dam Project Update
- San Jose Water Company – Vickery Tank Project
- BCI Featured in SMW Local 104 Fall Newsletter
- Emergency Ventilation Fans
- Rinconada WTP Residuals Management Project
- SFPUC San Antonio Pipeline (Sunol)
- Warm Springs tunnel ventilation
- VSFCD Influent Pump Station
- VTA Milpitas / Barryessa Extension Update
- VTA BRT Improvements nearing completion
- BART 19th Street Station Entrance Enclosure Pilot
- SSF WPCP Demolition Activities
Author Archives: Blocka Construction, Inc.
BCI awarded Oakmead Phase III Project
The third and final phase of the Oakmead Engine Replacement project was recently awarded to BCI. This $650,000 project will replace the final 2 engines at the Oakmead Storm Pump Station. Below are before and after pictures of an engine … Continue reading
Posted in Electrical, General Contracting, Mechanical
Comments Off on BCI awarded Oakmead Phase III Project
BART 480V Switchgear Replacement Phase II
This $6,000,000+ project includes replacement of aging electrical distribution panels and switchgear at 18 BART stations throughout Alameda and Contra Costa counties. Work includes de-energizing power to each station, which is only allowed during non-revenue hours. With work at 15 stations … Continue reading
Posted in Electrical, General Contracting
Comments Off on BART 480V Switchgear Replacement Phase II
Vineyard SWTP
Construction is in it’s last year for the Vineyard Surface Water Treatment Project. This project, involving construction of a brand new 50MGD Water Treatment Plant, has been underway since 2008. This $34 million contract consists of underground ductbanks, 4160V Distribution, 4160V … Continue reading
Posted in Electrical
Comments Off on Vineyard SWTP
Devil’s Slide Tunnel Update
Work continues on the Devil’s Slide Tunnel Project. Below are recent pictures showing the ventilation and supports in the equipment chamber, as well as some FRP ductwork being off-loaded and staged for installation for a fresh-air supply system.
Posted in Mechanical
Comments Off on Devil’s Slide Tunnel Update
BART 34.5kV Cable Upgrade
Work is now fully underway on the BART 34.5kv Cable Replacement project. This contract, in excess of $9,000,000, is the first phase of a series of projects planned for the replacement of aging power cables throughout the entire BART system. Work … Continue reading
Posted in Electrical, General Contracting
Comments Off on BART 34.5kV Cable Upgrade
Rinconada WTP Electrical Upgrades
BCI was recently awarded a $3.8 million dollar contract to upgrade the aging primary electrical, standby power, and PLC systems at the Rinconada WTP in Los Gatos, CA. Originally 4 separate projects, this larger, combined project allows BCI the ability to coordinate … Continue reading
Posted in Electrical, General Contracting
Comments Off on Rinconada WTP Electrical Upgrades
Harry Tracy WTP Long Term Improvements
BCI was recently awarded a $1.4 million dollar contract to replace several of the existing ventilation systems for the Harry Tracy WTP. The upgrades are part of a $174 million contract that was awarded to Kiewit Infrastructure West in February. The … Continue reading
Posted in Mechanical
Comments Off on Harry Tracy WTP Long Term Improvements
DWR Pumping Plant Control Systems Rehab
BCI was recently awarded a $5 million+ project with the Department of Water Resources to rehabilitate (3) pumping plants along the Sutter Bypass Canal and East Borrow Canal, located near Yuba City, CA. Work includes the installation of (E) 12kV Switchgear Lineups, … Continue reading
Posted in General Contracting
Comments Off on DWR Pumping Plant Control Systems Rehab
USD Boyce Road Lift Station
BCI was recently awarded a contract with GSE Construction, for the electrical and instrumentation work associated with the renovation of Boyce Road Lift Station. The (E) lift station will remain in operation, continuously receiving and treating sewage, duration construction. An entirely … Continue reading
Posted in Electrical
Comments Off on USD Boyce Road Lift Station
Los Vaqueros Dam Expansion Project
BCI was recently awarded a contract to provide and install the new electrical systems, seismic instrumentation, and analytical instrumentation systems for the Los Vaqueros Dam Expansion Project. This contract worth $1.3 million is a fast track project, expected to be … Continue reading
Posted in Electrical
Leave a comment